Page 82 - ANNUAL REPORT 2016
P. 82

Capital projects


            enniscorthy sewerage scheme – stage 3
            Upgrade in capacity of the Enniscorthy WWTP from 16,000 PE to 26,000 PE was tendered in
            2016 and work is due to start in 2017.


            enniscorthy and sow regional Water sewerage scheme
            Design of new intake and pumping station at Clonhaston with new rising main to Vinegar Hill
            WTP was approved.


            fethard-on-sea sewerage scheme


            Design of scheme with new WWTP and Pumping Station in progress during 2016.

            Gorey regional Water supply – south Wellfield


            The Gorey RWSS is to be upgraded and a new 8 Ml/day WTP and 7,500m3 reservoir built at
            Ballyminaun. The scheme is at design stage.

            Watermain rehabilitation


            The Wexford County Council direct labour crew replaced watermains at Kilhile,
            Adamstown, Stable to Cahore and Summerhill to Blackstoops.

            Wexford Town Watermain rehab and Gas network


            Design of scheme to replace watermains in Wexford town in conjunction with provision of new
            gas network.

            rationalistation of Water supply schemes


            Clohamon village was linked to Bunclody Water Supply Scheme. Hillview Court and Mayview
            Park in Oulart Village were connected to the Sow Regional Water Supply Scheme.

            Water Treatment plant upgrades


                                 Design of water treatment plant upgrades at Kilmallock and Taylorstown.
                                 Bunclody  Water  Treatment  plant  was  upgraded  to  provide  automatic
                                 coagulant dosing and UV treatment.


                                 Upgrades were provided at a number of treatment plants for PH correction.


                                     Water services performance indictor
             % of private drinking water schemes in compliance                                    92.34%


       80