Current Projects: 

  1. M11 Gorey to Enniscorthy PPP Scheme
  2. N25 New Ross Bypass PPP Scheme
  3. N11 / N25 Oilgate to Rosslare Harbour Project
  4. N30 Monyetucker to New Ross Scheme 

Phases of a Road Scheme

 The processes by which all NRA projects are undertaken are as follows:

  • Phase 1: Scheme Concept & Feasibility Studies

  • Phase 2: Route Selection

  • Phase 3: Design

  • Phase 4: EIA / EIR & The Statutory Process

  • Phase 5: Advance Works and Construction Documents Preparation, Tender & Award

  • Phase 6: Construction and Implementation

  • Phase 7: Handover, Review and Closeout